Residents help postpone major sewer works over winter

A MISERABLE winter of discontent for more than two thousand residents and businesses in Uppermill has been avoided after a utility giant listened to locals’ concerns.

United Utilities were planning carry out a major project costing nearly £1million from September to March to improve the local sewer network in sections of Church Road, New Street and Bolton’s Yard.

Project coordinator Chris Wheeler said engineers and highways officers talked to many local people about plans to temporarily close New Street and Church Road over winter, and agreed the three-mile diversion route may have been too difficult in extreme weather.

“Working in lovely, historic places like Uppermill, which have narrow, busy streets is never straightforward,” he said.

“We need to close the road so our staff and other road users are totally safe while we lay big pipes in often very deep trenches.  We also try to time our work to avoid events and festivities which are the life blood of local communities.

“We think the best thing is to slightly postpone the start of work until the weather is better, and we will work around village events as they happen.

“We remain totally committed to carrying out this work to vastly reduce the miserable problem of flooding from our sewers, which has been known to affect some homes in this part of Uppermill.

“But we are just as committed to doing it with the least disruption possible. I hope the changes we have made will allay some people’s concerns.”

P11 Church Road Exhibition Boards-3

As the project got underway in September with planned utility diversion work, residents were given the chance to look at maps for the six-phase project that will disrupt the village.

One resident was pleased with the schedule and told officers: “You’re doing it at the right time because of the weather.”

However one concerned lady added: “We already struggle with traffic on the smaller roads and won’t be able to cope with more.

“Some of the corners are blind and it will be so dangerous with more cars coming up and down.”

Anyone directly affected by the works will receive a letter informing them of the start dates and a flyer explaining why the work is necessary, when it will happen and the diversion routes.P11 Church Road Exhibition Boards-4

As well as scheduling works to avoid regular events, United Utilities has also pledged to carry out extra gritting of the diversion route during cold weather.

Work schedule:

Phase 1: Smithy Lane to Bolton’s Yard
Phase 2: Bolton’s Yard
Phase 3: New Street, from the Junction of Bolton’s Yard to Church Road
Phase 4: Continuing along Church Road to the junction of Pickhill Lane
Phase 5: From the junction with Pickhill Lane to outside house number 25
Phase 6: Continuing along Church Road to outside house number 35

Traffic restrictions are:

September 16 until December 16, 2013: Temporary traffic lights on Church Road between the junction with New Street and Pickhill Lane.

March until July, 2014:  Remaining road closures and diversions to allow new sewer pipes to be installed. Dates and details to be confirmed nearer the time.